The construction of the water desalination plant involves the execution of the industrial and service buildings, of water conduction pipe lines, of urbanization and of all installations as well as performing additional works.
  • Developer: Acuamed, S.A.
  • Construction Budget: € 69,461,551.01
  • Scope of works: Technical assistance in Health and Safety. Coordination of Health and Safety
Hydroelectric plant with a maximum gross jump height of 60.68 m and a maximum turbine power of 2978 kW. A 1900 mm pipe lines water conduction with a motorized butterfly valve. Hydroelectric plant designed for a nominal flow rate of 6 m3/s. Horizontal axis Francis type turbine. The work includes the installation and assembly of oil hydraulic unit of the turbine control and the By-Pass valve of the plant, valve guard and pipe insulation, bridge crane and ventilation equipment.
  • Developer: Andalusian Energy, S.L.
  • Construction Budget: € 2,119,497.20
  • Scope of works: Technical assistance in Health and Safety. Coordination of Health and Safety
Extension works of waste treatment plant providing it with new automated triage building for product recovery, new leachate treatment plant, expansion of refining compost plant and equipment automation.
  • Developer: Provincial Council of Granada
  • Construction Budget: € 17,950,789.65
  • Scope of works: Technical assistance in Health and Safety. Coordination of Health and Safety
Works for take apart and shutting down of tailings currently in combustion to a new location, returning the land to an acceptable standard with the establishment of a cloak of fertile land and subsequent reforestation, as well as the consolidation of the structure of mine galleries.
  • Developer: Railway Company from Madrid to Zaragoza and to Alicante, S.A. (M.Z.A.)
  • Scope of works: Technical Assistance in Mine Safety
Studies of safety conditions in the work were conducted according to the General Regulation of Mine Safety Basic Standards, the Technical Instructions of Safety and the Internal Safety Provisions, as well as an analysis of flammable gases content in the tunnel area and of ventilation air speed.
  • Developer: NECSO Entrecanales Cubiertas, S.A.
  • Scope of works: Technical Assistance in Mine Safety
The Espartal is a 2002 metres long tunnel with a two-way carriageway which is part of the Córdoba - Málaga high speed railway. Methane gas popped up at the construction stage after drilling a bore. Samples, tests and needed tasks were conducted to test its presence during the execution of two drillings ahead of tunnel works.
  • Developer: FERROVIAL-AGROMAN