Hidraulica y Medio Ambiente

Water-Waste Management

Project Design. Construction management. Technical Assistance to Construction Management
Construction of a sewage treatment plant of urban waste water. The sewage system used is based on low-cost maintenance model. It works by a pre-treatment containing fixed bars for thickness and a sandbox followed by a septic tank for decantation/digestion and peak attenuation, with a secondary treatment by constructed wetlands of subsurface flow (HAFSs), combining vertical (HAFSsV) with horizontal (HAFSsH) (hybrid system)
  • Developer: Provincial Council of Granada
  • Construction Budget: € 131,977.77
  • Scope of Work: Construction Project Design
Construction of breakwater wall in Jaen river downstream of Puente de la Sierra, to protect adjoining plots of possible overflow of the river. Large swivel is used with attached to the bucket for better handling of the breakwater clip.
  • Developer: Public Water Authority Guadalquivir
  • Construction Budget: € 1.200.000
  • Scope of Work: Monitoring and Control of the work
Adaptation of Río Salado bed, protective breakwater repair margin for slope stabilization under housing estate. The walking-excavator machinery is used due to their greater mobility and settlement.
  • Developer: Public Water Authority Guadalquivir
  • Construction Budget: € 1.200.000
  • Scope of Work: Monitoring and Control of the work
Construction of a new supply reservoir with a regulation capacity of 250 m3 on reinforced concrete and consistent supply networks in the supply pipes from the general network of Castillejar to the new deposit. Distribution pipes from the new reservoir to the population of Puente Arriba and tank drain pipes.
  • Developer: Granada Provincial Council
  • Construction Budget: € 161.832,39
  • Scope of Work: Construction Project Design
Construction of a prefabricated U-shaped channel of self-compacting concrete in sections of 9 m length, 2.30 m x 1.70 m dimensions, and 0.20 m thickness.
  • Developer: Public Water Authority Guadalquivir
  • Construction Budget: € 1.950.536,58
  • Scope of Work: Monitoring and Control of the work
  • Developer: Diputación de Almería
  • Construction Budget: 2.245.682,19 €
  • Scope of Work: Redacción del estudio de viabilidad